Central Place Construction Update 10-16-14

Night work within North Lynn Street is scheduled through 10/17. The majority of utilities have been completed and the remaining work is to restore the roadway. Restoration activities are expected to be less disruptive than the recent construction. After Friday 10/17, work will resume to the normal working hours.

Standard

Central Place Construction Update 10-6-14

As a result of the night shifts from 9/26 through 10/2, significant progress has been made on the utility work with N. Lynn. Street. Additional night shifts will resume tonight and end on Friday night (10/10). Prolonged periods of continuous noise is not expected. Clark has worked with their crews to minimized the noise created from the excavator. Similar to last week, traffic will be reduced to one lane of travel during the night shifts, with 3 lanes re-established by 6:00 am the following morning. We understand the inconvenience this poses and are working as quickly and safely as possible to complete the work and resume to our normal construction schedule.

Standard

Central Place Construction Update 9-25-14

Sanitary utility work within N. Lynn Street will begin this evening, Thursday, September 25th and continue to Saturday, October 4th. The night shifts will begin promptly at 9:00pm and end by 5:00am. Current dive aisle and pedestrian traffic patterns will remain as currently constructed.

Continual noise impacts (e.g. jack hammering / pile driving, etc.) are not expected. However, occasional construction related noise may be heard by residences located directly adjacent to the construction site. Your patience is appreciated and all reasonable measures will be taken to reduce this impact to the community.

Standard

Central Place Construction Update 6-20-14

N. Lynn Street Utility Work:

Current status of Travel Lanes and Sidewalks:

3 Lanes open / 3 lanes closed

Permanent Lane Closure – Working during daylight hours.

North Lynn Sidewalk – Closed

The Storm Sewer is complete and work on the sanitary sewer is ongoing.  The first structure was set this morning and work will progress towards the North.  The current traffic pattern will be in place throughout July during the sanitary work.

General:

Site demolition is complete and the pile installation will be completed by Tuesday 6/24.  This will allow for excavation operations to resume.  In accordance with our Maintenance of Traffic Plan, truck staging will occur from Lynn Street (entering and exiting the site).  Flaggers will be utilized during these operations to control traffic and maintain safety.

The 19th Street sidewalk will remain open to pedestrians for the duration with occasional closures.  Notifications will be sent prior to any changes in the current fencing and traffic configurations.  Once the soils are removed down to rock.

 

Standard

Central Place Construction Update 5-12-14

N. Lynn Street Utility Work:

Current status of Travel Lanes and Sidewalks:

3 Lanes open / 3 lanes closed

Permanent Lane Closure – Working during daylight hours.

Storm sewer installation is nearing completion and the western portion of asphalt roadway is being restored.
The sanitary sewer work will immediately follow. The sanitary install is a deep (20′) excavation and as such will require extensive shoring. During installation the traffic pattern will shift in accordance with the county approved MOT plan. This shift is expected to occur Wednesday or Thursday of this week and will consist of commuter traffic being split with two travel lanes on the east and one travel lane to the west. The existing western parking lane will be closed to parking and utilized as the travel lane. The middle three lanes of north Lynn will be utilized for construction and installation of the sanitary. Please follow the postaged signage.

General:

The McDonalds building has been demolished. General site demolition and pile installation are on-going. In the coming days, the remaining section of skybridge will be removed.

One bus lane on N. Moore street is closed, with the remaining 2 lanes open.

Standard

Central Place Construction Update 4-21-14

N. Lynn Street Utility Work:

Current status of Travel Lanes and Sidewalks:

3 Lanes open / 1 lanes closed

Permanent Lane Closure – Working during daylight hours.

Storm sewer installation is ongoing. The concrete traffic barriers and fencing have been relocated to the Western most lanes, with commuter traffic using the Eastern 3 lanes. This pattern will hold throughout this week and into next as the Storm Sewer installation nears completion.

General:

The McDonalds building will be demolished over the next 2 weeks. On Tuesday (4/15), temporary fencing was installed around the perimeter of the site. The following closures are in effect:

N. Moore – Sidewalk and 1 drive lane
N. Lynn – Sidewalk Closure

The fencing and barriers will be in this state for the next 4 weeks as we prepare to clear the site and begin excavation. By the end of next week – Clark will begin the pile installation and general site clearing.

Standard

Central Place Construction Update 4-11-14

N. Lynn Street Utility Work:

Current status of Travel Lanes and Sidewalks:

3 Lanes open / 1 lanes closed

Permanent Lane Closure – Working during daylight hours.

Pedestrian Closures – None

Storm sewer installation is ongoing. The concrete traffic barriers and fencing have been relocated to the Western most lanes, with commuter traffic using the Eastern 3 lanes.
This pattern will hold for the next 2 weeks.

Skybridge update:

The skybridge demolition work is complete over North Lynn and North Moore streets. One section of skybridge remains over the plaza area.

Demolition:

The McDonalds building will be demolished over the next 2-3 weeks. On Tuesday (4/15), site fencing will be installed around the perimeter of the site. The fencing and barriers will extend into 1 travel lane of N. Moore Street. See attached plan for reference.

Standard